The M5 Junction 10 Development Consent (Correction) Order 2025

This statutory instrument, the M5 Junction 10 Development Consent (Correction) Order 2025, formally amends errors found in the preceding 2025 Development Consent Order (DCO).

The Secretary of State made these corrections after receiving written requests from the applicant and National Highways, exercising powers under the Planning Act 2008, specifically to rectify issues concerning time limits, authority designations, and documentation references listed in the attached schedule.

Arguments For

  • The correction process ensures the legal instrument is technically accurate, upholding the legislative integrity of the original Development Consent Order (DCO) under the Planning Act 2008.

  • Addressing errors promptly, as requested by the applicant and National Highways, facilitates the smooth implementation of necessary infrastructure improvements for the M5 Junction 10 scheme.

  • Changes, such as adjusting timeframes (e.g., 42 days to 28 days) or clarifying responsibilities (e.g., substituting 'Secretary of State' for 'relevant planning authority'), clarify legal requirements and reduce potential ambiguities during project execution.

Arguments Against

  • The need for a correction order suggests initial drafting or scoping reviews were insufficient, potentially delaying the project timeline even if the correction itself is minor.

  • Amendments in a statutory instrument, even technical ones, introduce new legal text that requires careful monitoring by developers, regulators, and local authorities to ensure compliance with the updated terms.

  • Changes affecting documentation references (like appendix numbering in the environmental statement) might necessitate updating related procedural materials, adding an administrative burden.

The M5 Junction 10 Development Consent Order 2025

(“the 2025 Order”) which granted development consent within the meaning of the Planning Act 2008 (“the Act”), contained correctable errors within the meaning of paragraph 1(3) of Schedule 4 to the Act.

In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, before the end of the relevant period as defined in paragraph 1(6)(a) of Schedule 4 to the Act, the Secretary of State received written requests from the applicant and National Highways for the correction of errors in the 2025 Order.

In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State informed the relevant local planning authorities for the area in which the land to which the 2025 Order relates is situated, that the requests had been received.

The Secretary of State, in exercise of the powers conferred by section 119 of, and paragraph 1(4) and (8) of Schedule 4 to, the Act, makes the following Order.

Citation and commencement1.

This Order may be cited as the M5 Junction 10 Development Consent (Correction) Order 2025 and comes into force on 3rd November 2025.

Corrections to the M5 Junction 10 Development Consent Order 2025 (“the 2025 Order”)2.

The 2025 Order is corrected as set out in the table in the Schedule, where—

(a)

column 1 sets out where the correction is to be made;

(b)

column 2 sets out how the correction is to be made; and

(c)

column 3 sets out the text to be substituted, inserted or omitted.

ScheduleCORRECTABLE ERRORS

Article 2

(1)

Where the correction is to be made

(2)

How the correction is to be made

(3)

Text to be substituted, inserted or omitted

Part 3, Article 11(5)

For “42 days” substitute

“28 days”

Schedule 2, paragraph 11(3)(a)

For “relevant planning authority” substitute

“Secretary of State“

Schedule 10

In relation to the “environmental statement - appendix 1.1: glossary” for “0” substitute

“1”

Schedule 10

In relation to the “environmental statement - appendix 1.2: scoping opinion responses” for “0” substitute

“1”

Explanatory Note

(This note is not part of the Order)

This Order corrects errors and omissions in the M5 Junction 10 Development Consent Order 2025 (S.I. 2025/795), a development consent order under the Planning Act 2008, following two requests under paragraph 1(6)(a) of Schedule 4 to that Act.

Related

The Financial Services Act 2012 (Relevant Functions in relation to Complaints Scheme) (Amendment) Order 2026

Thu 2nd Jul 26

Amended the 2014 Order to update and clarify which regulatory functions of the FCA and PRA are eligible for investigation under the statutory Complaints Scheme.

Read More

The Air Navigation (Restriction of Flying) (Mill Lane, Chipping Ongar) (Emergency) (Revocation) Regulations 2026

Thu 2nd Jul 26

Revoked emergency flight restrictions in the vicinity of Mill Lane, Chipping Ongar, effective July 2, 2026.

Read More

The Digital Waste Tracking (England) Regulations 2026

Thu 2nd Jul 26

Established a mandatory digital system for tracking controlled waste in England, introduced a £26 annual operator fee, and granted the Environment Agency powers to issue civil penalties for non-compliance.

Read More

The Access to the Countryside (Coastal Margin) (Bawdsey to Aldeburgh) Order 2026

Thu 2nd Jul 26

Designated 24th June 2026 as the date ending the access preparation period for the coastal path between Bawdsey and Aldeburgh.

Read More