The Heckington Fen Solar Park (Correction) Order 2025

This order corrects errors in the Heckington Fen Solar Park Order 2025, a development consent order under the Planning Act 2008.

The Secretary of State approved corrections based on a written request from the applicant, which were then notified to the relevant local planning authorities.

The corrections amend several sections of the original order, updating references and coordinates, particularly in Schedules 1 and 13.

The effective date is April 14, 2025.

Arguments For

  • Addressing Inaccuracies: The corrections ensure the accuracy and clarity of the original order, preventing potential legal challenges or implementation issues.

  • Streamlined Project Execution: Correcting errors contributes to smoother development, avoiding delays and additional costs from correcting inaccuracies later.

  • Legal Compliance: The corrections ensure full adherence to the Planning Act 2008 requirements, upholding the legal framework governing the project.

  • Procedural Due Process: The corrections were made in accordance with the established procedures outlined in Schedule 4 of the Planning Act 2008, demonstrating transparency and fairness.

Arguments Against

  • Potential for Unforeseen Consequences: Although unlikely, correcting some parts of the order might have unintended effects on related aspects of solar park development or operation.

  • Resource Expenditure: Correcting the order requires resources from parties involved which could’ve been allocated elsewhere.

  • Time Delays: While the correction process aims for efficiency, there's a small potential for it to cause, however unlikely, marginal delays in the project timeline.

  • Alternative Approaches: Instead of corrections, perhaps the original order could have sought approval with improved due diligence and review before its initial passage.

  1. Citation and commencement (1) This Order may be cited as the Heckington Fen Solar Park (Correction) Order 2025. (2) This Order comes into force on 14th April 2025.
  1. Corrections The Heckington Fen Solar Park Order 2025 is corrected as set out in the table in the Schedule to this Order, in which— (a) column 1 sets out where the correction is to be made; (b) column 2 sets out how the correction is to be made; (c) column 3 sets out the text which is to be substituted, inserted or omitted.

SCHEDULE Corrections Article 2 [Table detailing specific corrections]

Related

The Financial Services Act 2012 (Relevant Functions in relation to Complaints Scheme) (Amendment) Order 2026

Thu 2nd Jul 26

Amended the 2014 Order to update and clarify which regulatory functions of the FCA and PRA are eligible for investigation under the statutory Complaints Scheme.

Read More

The Air Navigation (Restriction of Flying) (Mill Lane, Chipping Ongar) (Emergency) (Revocation) Regulations 2026

Thu 2nd Jul 26

Revoked emergency flight restrictions in the vicinity of Mill Lane, Chipping Ongar, effective July 2, 2026.

Read More

The Digital Waste Tracking (England) Regulations 2026

Thu 2nd Jul 26

Established a mandatory digital system for tracking controlled waste in England, introduced a £26 annual operator fee, and granted the Environment Agency powers to issue civil penalties for non-compliance.

Read More

The Access to the Countryside (Coastal Margin) (Bawdsey to Aldeburgh) Order 2026

Thu 2nd Jul 26

Designated 24th June 2026 as the date ending the access preparation period for the coastal path between Bawdsey and Aldeburgh.

Read More